Through our joint venture meps with Stantec Treatment, EPS delivered over £1m of off-site assemblies to the project.

Project Title

Utility

Client

MWHT/Severn Trent Water

Type

Lime Stabilisation / Mechanical DfMA Package

This was a strategic project for Severn Trent Water to secure water supply to Birmingham city.

Frankley WTW has capacity of 480MLD.

The project included:

  • New Lime Dosing Plant in existing Sludge Building to replace redundant lime plant

  • All packages designed in 3D, integrated with BIM software, factory manufactured, assembled, tested in-house and delivered safely in best practice configurations

  • Early engagement; 3D conceptual design; early site visits.

Our collaborative approach to this project involved:

  • BIM 4D scheduling introduced

  • Synchro used to work collaboratively with the design, construction, commissioning and planning teams, including the suppliers

  • Weekly scheduling sessions run on site

  • Linking the project 3D model with the delivery programme

  • Providing improved visibility and understanding of the construction/installation and commissioning phases

  • Helping to identify, understand and mitigate risks

  • Provide maximum confidence of the programme

Frankley Case Study
pdf