Tullich WTW

Description Summary

Through our joint venture meps with Stantec Treatment, EPS delivered off-site assemblies worth £4m on this project.

Project Title

Utility

Client

ESD/Scottish Water

Type

DAF/RGF/DfMA

The Tullich WTW is an 11.8 MLD water treatment plant.

This project consisted of:

  • Flocculation
  • Dissolved Air Flotation
  • Rapid Gravity Filtration

Our collaborative approach to this project involved:

  • BIM 4D scheduling introduced

  • Synchro used to work collaboratively with the design, construction, commissioning and planning teams, including the suppliers

  • Weekly scheduling sessions run on site

  • Linking the project 3D model with the delivery programme

  • Providing improved visibility and understanding of the construction/installation and commissioning phases

  • Helping to identify, understand and mitigate risks

  • Provide maximum confidence of the programme