Dundalk Pumping

Description Summary

This project by the EPS Group involved delivery of an accelerated project programme to include the retro-fitting of six existing pump stations.

Project Title

Utility

Client

Dundalk UDC

Type

DB

Works were carried out on live stations with an over-pumping requirement during works programme. 

Project delivery included the replacement of all pipework, valves, penstocks, screens, odour control, electrical control panels, plc and scada system. New pumps installed and commissioned included 7 No 116kw, 3 No 64kw, 3 No 29kw, 2 No 20kw and 2 No 16kw sewage pumps.

 

 

 

Get in Touch