Through our joint venture meps with Stantec Treatment, EPS delivered over £1m of off-site assemblies to the project.
Project Title
Utility
Client
MWHT/Severn Trent Water
Type
Lime Stabilisation / Mechanical DfMA Package
This was a strategic project for Severn Trent Water to secure water supply to Birmingham city.
Frankley WTW has capacity of 480MLD.
The project included:
-
New Lime Dosing Plant in existing Sludge Building to replace redundant lime plant
-
All packages designed in 3D, integrated with BIM software, factory manufactured, assembled, tested in-house and delivered safely in best practice configurations
-
Early engagement; 3D conceptual design; early site visits.
Our collaborative approach to this project involved:
-
BIM 4D scheduling introduced
-
Synchro used to work collaboratively with the design, construction, commissioning and planning teams, including the suppliers
-
Weekly scheduling sessions run on site
-
Linking the project 3D model with the delivery programme
-
Providing improved visibility and understanding of the construction/installation and commissioning phases
-
Helping to identify, understand and mitigate risks
-
Provide maximum confidence of the programme